Egypt Reports 71% Completion of 29.9 Million EGP Rashid Sea Wall Reinforcement
Synthesized from1 source

AI-generated summary
Egypt Reports 71% Completion of 29.9 Million EGP Rashid Sea Wall Reinforcement
The Ministry of Water Resources and Irrigation has announced that the 29.9 million EGP project to reinforce the Rashid sea wall has achieved 71% physical progress as of July 2026.
- Assistant Minister Mohamed Omar stated the project's cost is 29.9 million EGP and actual execution has exceeded the 65% target, reaching 71%.
- The project involves replacing damaged concrete blocks and adding new blocks in front of the wall to reduce wave force.
- Work includes strengthening the wall's base with heavy concrete blocks and installing protective rock layers with geotextile fabric to prevent soil erosion.
- Omar said the project began on March 5, 2024, and is scheduled to finish by May 5, 2027, and includes manufacturing 1,500 concrete blocks for emergency use.